Quick Summary
Electric van charging station installation requirements cover the competent person carrying out the work to BS 7671 and the IET Code of Practice, a site survey of supply capacity and earthing, any planning or landlord consent, and load management where power is shared. The installation must then be tested, certified and commissioned before handover.
- A competent person must work to BS 7671 and the IET Code of Practice for Electric Vehicle Charging Equipment Installation.
- Survey the full planned build-out, not just the first charger, to avoid disruptive retrofitting later.
- RCD protection, overcurrent protection and an isolation switch must all be in place.
- Load management lets depots charge a fleet without an expensive supply upgrade.
- Do not sign off without the certificate, test schedule and commissioning records.
Table of Contents
- What the Electric Van Charging Station Installation Requirements Cover
- Who Counts as a Competent Person Under BS 7671
- EV Charger Site Survey for Businesses: What to Assess Before You Commit
- Electrical Supply, Consumer Unit and Earthing Arrangements
- EV Charger Planning Permission UK: What Vans Depots Actually Need
- Workplace Charging Load Management and Network Capacity
- Building an Electric Van Fleet Charging Strategy
- Charger Power Ratings, Charging Speeds and Off-Street Parking
- Commissioning Your Electric Van Charging: Next Steps with OVL Group
- Frequently Asked Questions
What the Electric Van Charging Station Installation Requirements Cover
Electric van charging station installation requirements are the technical, legal and practical conditions a site must meet before a charge point can be safely commissioned. They cover who may carry out the work, how the electrical supply and earthing must be arranged, what permissions are needed, and how the charger is tested and certified afterwards.
Below, we break down the key requirements that decide whether your depot is ready, what a site survey should test, and how to plan charging around a growing electric van fleet.
Who Counts as a Competent Person Under BS 7671
A competent person is someone with the training, qualifications and experience to carry out electrical installation work safely and to the required standard. For charge point work, that means a qualified electrician who works to BS 7671, the UK's wiring regulations, and to the IET Code of Practice for Electric Vehicle Charging Equipment Installation.
That document sets out supply capacity checks, earthing arrangements and protection requirements.
Use this checklist before you appoint anyone:
- Evidence of current electrical qualifications and registration
- Named standard: BS 7671 and the IET Code of Practice
- Experience with commercial, not just domestic, charge points
- A written certificate and test schedule on completion
- Confirmation of who handles notification and handover documents
EV Charger Site Survey for Businesses: What to Assess Before You Commit
An EV charger site survey for businesses is a structured inspection of your site's power supply, parking layout, cable routes and existing electrical infrastructure. It happens before any equipment is ordered, and it decides what is actually feasible.
The survey should answer four questions:
- How much spare capacity does the existing supply have?
- Where will the chargers sit, and how far is that from the distribution board?
- What earthing arrangement does the building use?
- What cable route is safe, short and practical?

A common mistake is surveying only the first charger. If you plan to add units later, the survey must cover the full build-out. Retrofitting capacity is far more disruptive than designing for it once.
For a practical walkthrough of depot power checks and grant options, read our guide on how to plan electric van charging infrastructure for SMEs.
Rural Sites and Outbuildings
Two things need checking early:
- Cable distance. Long runs affect voltage drop and cable sizing, so the route matters as much as the load.
- Outbuilding supplies. A shed or barn with its own small supply may not support a charger without an upgrade.
Get this assessed before you sign a lease. It is the most common cause of delay on rural fleet electrification.
Electrical Supply, Consumer Unit and Earthing Arrangements
The electrical supply is the foundation of the whole installation. Before a charger goes in, the consumer unit or distribution board must have a spare way, the supply must have capacity, and the earthing arrangement must suit the charger.
Supply type matters: a single-phase supply has less headroom than three-phase, which is why depots running several vans often need a three-phase connection to charge more than one vehicle at a time.
Earthing needs a specific check. Many UK properties use a PME arrangement, and the IET Code of Practice sets out what that means for charge point installation (The IET Code of Practice for Electric Vehicle Charging Equipment Installation, 4th Edition).
IET Code of Practice for Electric Vehicle Charging Equipment Installation
Watch out: a charger added to a board with no spare capacity, and no load calculation behind it, is a safety problem waiting to happen.
RCD Protection, Overcurrent Protection and the Isolation Switch
Three protective elements must be in place:
- RCD protection to guard against earth leakage and electric shock
- Overcurrent protection to protect the circuit and cable
- An isolation switch so the charger can be safely shut down for maintenance
Some charge points include built-in protection, which changes what the installer needs to add at the board. That decision belongs to the competent person, not the buyer.
EV Charger Planning Permission UK: What Vans Depots Actually Need
EV charger planning permission UK requirements depend on the building, the site, the number of units and whether the property sits in a conservation area or is listed. Check with the local planning authority before work starts.
Planning rules differ across the UK nations, so a fleet operating across borders should not assume one position applies everywhere. Confirm the rules for each site with the relevant planning authority.
Three checks matter for a van depot:
- Building status. Listed buildings and conservation areas restrict what can be mounted externally, and the local planning authority will expect a heritage statement for anything visible from a public highway or affecting the setting of a listed structure.
- Landlord permission. If you lease the yard, get written consent before work starts. A commercial lease will usually require landlord's licence to alter, and that process runs on its own timetable separate from planning.
- Local authority confirmation. For anything unclear, confirm with the local planning authority rather than assuming. A pre-application enquiry is cheaper than a retrospective application.
Older and listed properties can limit where equipment may go, so check first and install second.
Ask the local planning authority to confirm in writing before you order equipment.
Workplace Charging Load Management and Network Capacity
Workplace charging load management spreads the available power across chargers so the site does not exceed its supply. Instead of every van drawing full power at once, the system balances the load and keeps the connection within limits.
This is how depots charge a fleet without an expensive supply upgrade.
Network capacity is the other half. If your site needs a new or larger connection, the distribution network operator handles it, and that takes time, build it into your timeline early.
Smart charging adds control. It lets you shift charging to cheaper overnight periods and avoid peak demand charges.
Ofgem guidance on electricity connections and network capacity
Building an Electric Van Fleet Charging Strategy
A charging strategy connects your vehicles, your routes and your power. It is a plan for how the fleet gets charged, by whom, and in what order, not a list of chargers.
Four elements belong in it:
- Duty cycles. How far do your vans travel, and when do they return?
- Overnight capacity. How many vehicles can charge at once, and for how long?
- Driver rules. Who plugs in, when, and what happens if they forget?
- Cost control. When is power cheapest, and how do you avoid peak charges?
For the full roadmap covering planning, infrastructure, costs and incentives, see our guide on transitioning your company fleet to electric vehicles. If you need to formalise charging rules and driver eligibility, our article on how to write an electric vehicle fleet policy walks through it step by step.
| Requirement | What It Covers | Who Owns It | Timing |
|---|---|---|---|
| Competent installer | BS 7671 and IET Code of Practice | Contractor | Before work starts |
| Site survey | Supply, layout, cable routes | Contractor and fleet manager | Before ordering |
| Supply and earthing | Capacity, PME, protection | Contractor | Survey stage |
| Planning and landlord consent | Building status, lease terms | Fleet manager | Early |
| Load management | Power balancing, smart charging | Contractor and DNO | Design stage |
| Commissioning | Testing, certification, handover | Contractor | At completion |
Charger Power Ratings, Charging Speeds and Off-Street Parking
Charger power ratings decide how fast a van charges, but speed depends on both the charger and the vehicle's onboard charger. A higher-rated unit will not speed up a van that cannot accept the power.
For most depots, the practical split is:
- Overnight charging: lower power, more units, cheaper to install
- Rapid top-up: higher power, fewer units, heavier supply demand
Off-street parking is a requirement, not a preference. Chargers need a fixed parking space with a safe cable route, and the cable must not trail across walkways or public highways.
Weatherproof enclosures matter on exposed rural sites. So does cable management: untidy cables get damaged, and damaged cables get condemned.
For urban delivery fleets weighing the case for electric vans, our article on the benefits of electric vans for urban delivery fleets sets out the cost and emissions picture.
Commissioning Your Electric Van Charging: Next Steps with OVL Group
Commissioning is the handover moment, where a good installation is proved or exposed.
A proper commissioning sequence for a van depot looks like this:
- Initial verification. Dead testing of insulation resistance, continuity and polarity before the supply is energised, recorded on an appropriate electrical certificate depending on scope.
- Live testing. Earth loop impedance, RCD trip times and functional checks, including a test charge on a vehicle that can accept the full rated current.
- Documentation. The certificate, test schedule, manufacturer's commissioning record and IET Code of Practice checklist, handed over as a single pack.
- Notification. The installer should confirm who is responsible for any notification and compliance certification before work starts.
- Network operator confirmation. If a new or upgraded connection was required, confirm the distribution network operator has recorded it and that supply capacity matches the design.
Watch out: a charger that powers up and charges a van is not the same as a commissioned installation.
This is where OVL Group comes in. If you are still deciding between outright purchase and rental, our current van leasing special offers show what is available.
If you are comparing options before you commit, our electric and hybrid leasing range is the place to start. Charging requirements are technical, and getting them wrong is expensive.
Get started with OVL Group and build an electric van fleet that is ready to charge from day one.
Charging infrastructure is only half the decision. The other half is the vans themselves, and how you finance them.
Frequently Asked Questions
Do I need planning permission to install an electric van charger in the UK?
The rules are tighter for listed buildings, conservation areas and sites with specific local restrictions. Check with your local planning authority before work starts, and always get landlord permission if you rent the premises. A site survey should confirm whether EV charger planning permission UK requirements apply to your depot.
Does a business need to notify its electricity network operator before installing EV chargers?
Yes, in most cases. Larger installations, particularly those adding significant load, require notification to your distribution network operator so it can confirm network capacity. The connection process can take time, so start it early in your electric van charging project. Your installer or a fleet consultant can advise on the application and any supply upgrade that follows.
How many chargers does an electric van fleet need?
It depends on duty cycles, shift patterns and dwell time. Vans that return to base overnight can often share chargers on a rota, while multi-shift operations need more units. A workplace charging load management system lets you install fewer chargers without compromising availability. Map your routes and return times before sizing the installation.
What electrical safety requirements apply to workplace EV charger installation?
Installation must comply with BS 7671 and follow the IET Code of Practice for EV charging equipment. That means a dedicated circuit, suitable RCD protection, correct earthing arrangements and an isolation switch. A qualified electrician should complete the work, test it and issue the electrical certification. Keep the handover documents for your compliance records.